CMWSSB shall pay CWDL for the Quantity of desalinated Sea water that it shall Off-take from the Plant as per the provisions of the BWPA.

Scope of the work

The Project Developer shall Design, Build, Own, Operate and Transfer 100 MLD Sea Water Desalination Plant. The detailed scope of work shall be; Detailed Design, Engineering, Financing, Procurement, Off-take of water from the sea, treatment of sea water including by Reverse Osmosis (RO) to the required quality of product water, construction of underground tank for treated water, safe disposal of concentrate (brine) and other wastes from the Plant as per stipulated norms of Pollution Control Board, Operation & Maintenance of the Plant for a period of 25 years.

Details of the BWPA between CMWSSB and CWDL

»Date of Letter of Intent (LOI)
»Date of BWPA signed in the presence of Hon’ble Chief Minister of TamilNadu
»Vacant Possession of the Site
»Conditions Precedent
»Commercial Operation Date C.O.D
»Operation Period
»Project Phases
»Power supply to the plant
»Clearances
»Product water specifications


Date of Letter of Intent (LOI)
04-Aug-2005

Date of BWPA signed in the presence of Hon’ble Chief Minister of TamilNadu
13-Sep-2005

Vacant Possession of the Site
Land is in the possession of CWDL since 14.10.05 as per the Land Lease agreement with CMWSSB. The Land Lease is for a period of 27 yrs.

Conditions Precedent
Set of Conditions to be satisfied by both parties of the BWPA before the rights and obligations of the parties become effective.

Commercial Operation Date C.O.D
The date on which CWDL commences sale of Desalinated water, after the plant is certified by CMWSSB for commencement of Operations.

Operation Period
25 yrs from the C.O.D

Project Phases
Phase–I: 15 Million Litres per Day (MLD), Phase-II: 85MLD. Phase I & II to be completed within the Construction Period of 15 months.

Power supply to the plant

The total power requirement and uninterrupted supply for the project shall be made available by CMWSSB / GoTN. The cost of power consumed shall be borne by CWDL.

Clearances
CWDL is responsible for obtaining any and all clearances required for setting up of the Proposed plant.

Product water specifications
The product water should conform to IS Standard 10500 : 1991


 
Chennai Water Desalination Ltd.
Environmental Impact Assessment