On 4-Mar-09 CEIG has accorded the approval for New HV/MV & LV Electrical Installations of the Desalination Plant units. On 13-Jan-2010 CEIG has accorded the approval for New HV/MV & LV Electrical Installations of Stand-by Intake Pump-house.
iii) Permission
from Tamil Nadu Maritime Board:
• Granted Lease for the required Coastal
Land on 15-Nov-2005
• Granted Approval for Marine Constructions/Off-shore
Marine Facilities on 23-Nov-2005
iva) Tamil
Nadu Pollution Control Board:
Issued
‘No Objection Certificate’ on 26-Oct-2005.
'Consent
to Establish' issued on 17-Nov-2006'.
ivb) 'Consent
to Operate' Registered on 31-Mar-2010'; Regn. No. CC10932; Consent Fee paid.
v) Permission for Cutting of Trees:
No trees at the
Proposed Land. Not Applicable
via) Plan Approval
from Inspector of Factories: Obtained;
vib) Final As built plan (Revised Plan) submitted to the Chief Inspector of Factories:
vic) Applied for Factory License from the Deputy Chief of Factories Inspector, Thiruvallur District. Site Inspection Completed on 04-May-2010; 'Factory Licence Obtained on 27-May-2010'
vii) Permit for Plan and Construction of Buildings, Structures,
in accordance with applicable building bye laws:
Obtained
viii) License from Labour Commissioner:
Obtained
ix) License from Fire & Rescue Services of Tamilnadu Government: Obtained on 18-Nov-2009
MINISTRY OF FINANCE, GOVERNMENT OF INDIA
STATUS OF CLEARANCE
• FIPB issues Approval Letter to CWDL on 9-Jan-2006
• FIPB Approval Letter dated 9-Jan-2006 to CWDL, includes,
grant approval for Import of Equipment and Machinery
for Construction and Operation
For this CWDL approached FIPB Unit for Approval on 17-Oct-05
Documents Submitted to FIPB
• Checklist
• Memorandum of Association
• Details of Projects undertaken by IVRCL
• Details of On-going projects of IVRCL
• Details of Projects successfully completed by IVRCL
• Audited Financial statements of IVRCL
• Business Structure of BEFESA
• Details of Activities carried out by BEFESA
• Brochure giving profile to BEFESA
• Details of the projects undertaken by BEFESA
• Audited Financial Statements of BEFESA
• Fundamental Objectives and Details of the Proposed Project
• Project Report
• LOI for setting up of desalination plant by CWDL (Special
Purpose Vehicle of IVRCL & BEFESA)
• Declaration from BEFESA stating No Joint Ventures/Collaboration
in India
Ministry of Urban Development seek information from CWDL vide
letters dated 16-Dec-05 and 22-Dec-05
CWDL submits additional Information to Ministry of Urban Development
on 22-Dec-05
• CWDL Board resolution dated 9-Nov-2005 regarding increasing
of Authorized Share Capital as per requirements
and related documents
• Approval letter from Tamil Nadu Maritime Board granting
permission to draw seawater and set up
Off-shore Marine Facilities (In-take & Out-fall
systems)
• Letter stating the Product Water conforming to IS Standards
• Reject Brine Discharge characteristics conforming to the
TNPCB standards for disposal to Sea.
FIPB
grants approval on 9-Jan-2006
MINISTRY OF ENVIRONMENT
AND FOREST CLEARANCE
STATUS OF CLEARANCE
• MOEF
issues CRZ Clearance Letter to CWDL on 26-Oct-2006; Amendment to CRZ Clearance Letter on 23-Mar-2010
CWDL Submits application to
TNPCB
• Submitted application for obtaining
Environmental Clearance as per CRZ notification on 5-Oct-05
CWDL Makes Technical Presentation to Experts of District
Level Coastal Authority
• Presentation to District Level Coastal Authority Meeting
at Thiruvallur District Collectorate on 6-Oct-2005
• CWDL makes Technical Presentation to Expert Members of
Tamil Nadu State Coastal Zone Management Authority
• Technical Presentation to Expert Members of Tamil Nadu
State Coastal Zone Management Authority on 24-Oct-2005
• Tamil Nadu State Pollution Control Board issues ‘No
Objection Certificate’
TNPCB issues ‘No Objection Certificate”
on 26th October 2005, to CWDL with the condition that ‘ Consent
to Establish’ will be issued subject to clearance under
CRZ notification by MoEF GOI.
• Secretary to Government
of Tamil Nadu (Environment and Forests Department) forward the
recommended proposal to The Chairman, National Coastal
Zone Management Authority, MoEF for CRZ clearance
on 29-Oct-2005
CWDL submitted ‘Questionnaire’ and ‘Application’
to MoEF Delhi along with the EIA report on 30th October 2005.
• CWDL makes Technical Presentation for Ministry of Environment
and Forests clearance Technical Presentation
to the Reconstituted Expert Committee on Infrastructure Development
and Miscellaneous Projects, on 29-Nov-2005
• Letter
received from MoE&F dated 28-Dec-2005.
• In response to the queries
raised by MoE&F vide their letter dated 28-Dec-2005, CWDL
has taken the following action :-
CMFRI STUDIES
1. CWDL approaches CMFRI for conducting Impact Studies on Marine
Biological Entities
• CWDL submitted formal request to CMFRI, Kochi to conduct
‘Impact Studies on Marine Biological Entities’
on 31-Dec-2005
• 4-Jan-2006 - CWDL executive met CMFRI scientists
to enquire regarding the application to conduct the studies
suggested by MoE&F.
• 5-Jan-2006 - CWDL submitted Project details to CMFRI
on 5-Jan-2006.
• 12-Jan-2006 - CMFRI scientists visited the proposed
Desalination Plant site and interacted with the local fishing
community.
• Five Reminder Letters were sent to CMFRI, Kochi
to expedite Studies on 9-Jan-2006, 18-Jan-2006,
24-Jan-2006, 15-Feb-2006, 20-Feb-2006, 24-Feb-2006.
• On
25-Feb-2006, CMFRI submitted project proposal and MoU Format to
CWDL for conducting the studies on “Rapid
Impact Assessment of high saline effluent from the proposed desalination
plant at Minjur, on the coastal marine life
and fishery”.
• On 28-Feb-2006,
CWDL accepted the project proposal and CMFRI approved and signed
the MoU for conducting the studies on “Rapid
Impact Assessment of high saline effluent from the proposed desalination
plant at Minjur, on the coastal marine life and fishery”.
• On 12-Jul-2006, CMFRI completed the Final Report
of Consultancy on “Rapid Impact Assessment of high saline
effluent from the proposed desalination plant at Minjur, on the
coastal marine life and fishery”
2. On 02-Jan-2006, CWDL replied to MoE&F letter dated 28-Oct-2005
wherein various additional information sought, was furnished.
•
On 10-Jan-2006, MoE&F sends letter seeking more Information/Details
for further necessary action
• In reply to the MoE&F letter dated 10-Jan-2006, CWDL
furnished the following on 13-Jan-2006 ;
1. CWDL submited report on ‘Terrestrial Environment and
Management (Supplementary Report)’
2. CWDL requested for ‘Consent to Establish’ with
condition that ‘Consent to Operate’ will be issued
only after the CMFRI study is completed
and mitigative measures, if any, suggested by CMFRI, shall be
employed.
• On
18-Jan-2006, MoE&F sends letter to CWDL seeking more Information/Clarifications
for further necessary action. MoEF asks CWDL to submit
CMFRI report in this letter.
• On
25-Jan-2006, CWDL replied to the MoE&F letter dated 18-Jan-2006.
• On 11-Feb-2006, CWDL submitted letter to the MoEF stating
that CWDL had already submitted clarifications
on 13-Jan-2006 and on 25-Feb-2006 to their comments. CWDL requested
MoEF to consider according CRZ clearance enabling
CWDL to start construction activity and the ‘Consent to
Operate’ can be issued by TNPCB subject
to the condition of implementation of CMFRI findings.
• On 19-Jul-2006, CWDL submitted CMFRI report to MoEF
and requested to issue CRZ clearance
vide letter dated 15-Jul-2006.
• On 26-Oct-2006, MoEF issued
CRZ Clearance for setting up of 100 MLD Desalination Plant and allied
activities at Kattupalli Village, Ponneri Taluk,
Tiruvallur District, Tamil Nadu by CWDL
NAVIGATIONAL SAFETY ON PORTS COMMITTEE
STATUS OF CLEARANCE
• On 12th April, 2006, NSPC issued Provisional In-Principle
NOC
CWDL submitted request to Navigational Surveyor, NSPC on 20-Oct-05
Documents attached along with the request
• Memorandum & Articles of Association
• Topographic Map showing location of Desalination Plant
• Process flow diagram of the Desalination Plant
• Detailed Process description of the Desalination Plant
Additional details submitted to Nautical Advisor,
Directorate General of Shipping, Mumbai on 17-Jan-06
• Intake and Out-fall system (Cross section and Layout)
• Bathymetry
• Topo Map of the Plant Area
• Capture Facilities attached to the Intake System
• Tamil Nadu Maritime Board approval dt. 23-Nov-05 for Marine
constructions and Off-shore Marine Facilities to
draw seawater
Standard Proforma for Safety Navigation in Ports submitted on
27-Jan-06
The proforma consists of IV parts
Part-I: Port Development Plan
Part-II: Operations
Part-III: Navigation Chart/Publications Update Service
Part-IV: Navigation Chart/Publications Aids to Navigation
Furnished Additional details as sought by the Nautical Surveyor
on 30-Jan-06
Satellite Imagery
Intake and Out-fall system layout
• On 10-Feb-2006,
Directorate General of Shipping sent letter to CWDL provide with
two clarifications regarding the NSPC clearance.
• On 27-Mar-2006, CWDL made presentation to NSPC for obtaining
NOC laying Pipelines, Intake Towers and Outfall Diffusers in the
Sea.
•On
12-Apr-2006, NSPC issued Provisional In-Principle NOC for the
project.
•On
21-May-2007, NSPC extended Provisional In-Principle NOC for the
project till 30-Apr-2008.
•On
12-Jun-2008, NSPC extended Provisional In-Principle NOC for the
project till 31-Aug-2008.
GOVERNMENT OF TAMILNADU/LOCAL AUTHORITIES
STATUS OF CLEARANCE
• Composite
“In Principle” Clearance Accorded
To avoid ANY PROCEDURAL DELAYS,
Government of Tamilnadu vide GO MS 588 Industries (MIB.1) dated
10-Sep-98 have established Effective SINGLE WINDOW SYSTEM to accord
all related CLEARANCES/APPROVALS/REGISTRATIONS/CERTIFICATIONS
CWDL submitted Common Application Form for Single Window Clearance
on 10-Oct-05
• The application form submitted to Tamilnadu Industrial
Guidance & Export Promotion Bureau, Single Window
Facility : Documentation & Clearance
Centre, A nodal agency of Industries Department, Government
of Tamilnadu
• The Common Application form is submitted for scrutiny
of various statutory agencies of Tamilnadu.
PRE-PROJECT CLEARANCES
I Local body clearance
Site and building plan approval
Health Clearance
Fire Service Clearance
II Environmental Clearance from Tamilnadu Pollution Control Board
III Registration with Inspector of Factories under Factories Act
IV Boilers Registration
INFRASTRUCTURE SUPPORT
I Application for Land Support
II Application for Water Supply
III Application for Power Supply
IV Safety Certificate from Chief Electrical Inspector
DOCUMENTS SUBMITTED TO THE DOCUMENTATION & CLEARANCE CENTRE
ON 10-OCT-05
• Detailed Building Plan, Elevation and Section of the Plant
units
• Layout of the Units of Desalination Plant and Type of
Machinery proposed
• Site Layout Plan showing Access, Boundaries along with
extent of land purchased
• Detailed Topo plan showing the Development around the
Proposed Site
• Villance plan showing Survey Numbers
• Lease Deed of the Land
• CWDL on Invitation from Documentation and Clearance Centre
made Presentation on 25-Oct-05
• Project Details presented at the Meeting attended by Authorized
Representatives of the concerned departments for according
Clearances/Approvals
• CWDL submitted necessary documents to The Department of
Inspectorate of Factories as per their requirements
on 7-Nov-05.
• High Power Single Window Committee – Project Approval
Authority (PAA) Chaired by Chief Secretary, Government
of Tamilnadu accorded COMPOSITE SINGLE WINDOW CLEARANCE. On 9-Dec-05.
• FINANCIAL CLOSURE ACHIEVED ON 25TH-JAN-2007
• INAUGURATION BY HON'BLE CM OF TN ON 25TH-FEB-2007
• EFFECTIVE DATE INTIMATED BY CMWSSB AS 16TH-MAY-2007 BASED ON COMPLIANCE CERTIFICATE ISSUED BY INDEPENDENT CONSULTANT
• AWAITING THE INSTRUCTIONS FROM CMWSSB FOR THE PERFORMANCE TESTING OF THE FACILITY TO ACHIEVE COMMERCIAL OPERATIONS DATE.
• CONSTRUCTION PERIOD PHOTOGRAPHS
• FEBRUARY 2007
• MARCH 2007
• APRIL 2007
• MAY 2007
• JUNE 2007
• JULY 2007
• AUGUST 2007
• SEPTEMBER 2007
• OCTOBER 2007
• NOVEMBER 2007
• DECEMBER 2007
• JANUARY 2008
• FEBRUARY 2008
• MARCH 2008
• APRIL 2008
• MAY 2008
• JUNE 2008
• JULY 2008
• AUGUST 2008
• SEPTEMBER 2008
• OCTOBER 2008
• NOVEMBER 2008
• DECEMBER 2008
• JANUARY 2009
• FEBRUARY 2009
• MARCH 2009
• APRIL 2009
• MAY 2009
• JUNE 2009
• JULY 2009
• AUGUST 2009
• SEPTEMBER 2009
• OCTOBER 2009
• NOVEMBER 2009
• DECEMBER 2009
• 2010 UPDATES
• DEVELOPMENT OF ARTIFICIAL REEF STRUCTURES BY CWDL ON 30-MAR-2009
• SINKING OF 210 NOS. ARTIFICIAL REEF STRUCTURES BY CWDL ON 27-SEP-2009
EXCERPTS OF DISCUSSION
Between
REPRESENTATIVE OF CWDL and EXPERT FROM MADRAS INSTITUTE OF DEVELOPMENT
STUDIES (MIDS), who has done critical evaluation on Desalination
Plant.
::
Home | History
| CWDL | EIA
| Proposed Plant |
Events | Video Clips | Contact
us ::